I would appreciate some advice on the sequence of my BW-BPS Transport

Following is what I am about to perform :-

1) In BPS0, Tool -> Transport Menu ;

Pick my 'Planning Area' with Option 'New Transport Including All Planning Levels'

Create a Customizing Request then export

2) In RSA1 -> Transport Connection, Collect my BPS InfoCube with 'In Data Flow Before and After'

Create a Customizing Request, then export

Please correct me if I`m wrong or any better best practise suggestions would also help!

Which sequence should be initiated first ?

Thanking in advance!

Message was edited by: John Mcluskey

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

First of all the RSA1 request will be a workbench request and not a customization request. The correct order is to move the cube first and then the planning area.

thanks

Former Member
0 Kudos

Thanks Jain,

My next issue is that although I`ve tranported the Cube and the Planning Areas, however the Planning Folder did NOT get transported.

Could you please advice ?

Former Member
0 Kudos

Hi,

you can use program UPC_TRANSPORT_BPS_ALL to transport BPS Object. For the P folder: /nUPSPM (Customizing) --> Extra --> Transport Folder.

Best Regards,

Suan Liono