Difference between PR and PO Value

0 Kudos

Take a look at the Scenario

If PR is made for 900,000 USD, and PO for 200,000 USD, (Account Assignment Tab of PO, give

WBS Element No), would it be possible to track the costs in the Reports in PS.

Accepted Solutions (0)

Answers (4)

Answers (4)

0 Kudos

Thank you.

Former Member
0 Kudos

check Transactions ME5J for PR and ME2J for PO

Regards,

Nitin

nitin_patoliya
Active Contributor
0 Kudos

As suggested by amit you can check CJI5 & CJI3 report. From there you can drill ldown to all line item reports like TP/ GR/ IR etc... I believe you have to properly use this reports.

CJI3 >Feed data & Execute>Environmet & explore.

Regards

Nitin P.

Former Member
0 Kudos

Yes..you can track the commitments of PR and PO. Go to CJI5 report.

Actual cost will come once u do GRN against PO. It will increase Actual cost and reduce commitment against PO.

Former Member
0 Kudos

Try S_ALR_87013542- Act/Comm/Total/Plan

This shows your commitment.

Another one is ME5J - Purchase requisitions for projects .This gives you a track of PO against the said PR, GR ag the PO, Invoice Ag the PO.