on 04-07-2009 5:51 PM
Hi
I'm having a deadlock problem in table S004 of LIS.
In the OSS sugest that use the V3 update method for that table, in the transaction OMO1. I talk with the funcionals and they say to me that is OK to configure it.
I do that and I send via transport to QAS but the table has not been upgrade anymore from that date.
I also read that the collective run is done by a report, the RSM13005, but i don´t know if:
1) I have to schedule in background?
2) How many times a date?
3) With which parameters?
4) What is the function module that affect that table?
5) If i lossing any other detail?
Thanks in advance
Hi,
Have got any answer for using the program RSM13005 to clear up the V3 updates?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.