on 04-07-2009 9:33 AM
Can bubget be controled against statistical WBS element?
Hi Mikhail,
Yes you can use Statistical WBSE for Statistical Budget Monitoring/Control.
When you use Statistical WBSE as cost object in some transaction no real cost will be posted to this WBSE (Only Statistical cost will be posted for budget control purpose)
Actual Cost will automatically go to the u2018Actual Cost Centeru2019 which you'll have to maintain in the WBS element data.
Write back in case you need more details.
with regards,
Ravi Shrivastav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
yes. See note 178837.
Kind regards
Peter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi mikhal,
did u try the below option .
edit ->statuslock-->budget .. you can lock budgeting on particular WBS ..
regards
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.