Can bubget be controled against statistical WBS element?

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Mikhail,

Yes you can use Statistical WBSE for Statistical Budget Monitoring/Control.

When you use Statistical WBSE as cost object in some transaction no real cost will be posted to this WBSE (Only Statistical cost will be posted for budget control purpose)

Actual Cost will automatically go to the u2018Actual Cost Centeru2019 which you'll have to maintain in the WBS element data.

Write back in case you need more details.

with regards,

Ravi Shrivastav

Former Member
0 Kudos

Hi Ravi,

There are two cost centers in WBSE:

Resp. cost cntr

Req.cost center

Which one should be used to post actual cost for statistical WBSE?

former_member203108
Active Contributor
0 Kudos

Go to Control tab of WBSE...u will see statistical indicator next to that u will see CCtr. Post...use that cost center field.

Former Member
0 Kudos

Hi,

yes. See note 178837.

Kind regards

Peter

Former Member
0 Kudos

hi mikhal,

did u try the below option .

edit ->statuslock-->budget .. you can lock budgeting on particular WBS ..

regards