Dear Gurus

I have got a work center where production goes on in shifts the machines run for 24hrs .In the work centers I have customized like that only mentioned three shifts from 6am to 2pm from 2pm to10pm and from 10pm to 6.00am.But if any production in this work center is getting completed after midnight the date is getting changed to the next day. Ideally the date should change after 6am after the end of c shift.Why is it happening?Where is the setting?


Sandip Sarkar



It is obviously possible to full fill your requirement. But it needs a development. The total development can be done specific to user even To do the same, to need to the development in the program "SAPMM07M" , in the screen number 0300.

We have done the same thing in the present project....let me collect the code....

What we did, when we are doing the GR ( MB31) the posting w'nt change before 6am.Upto 6 am, the date will be of the previous date.

Hope, this developmemt will suffice your requirement.