Multiple counter plan

Former Member

Hi Experts,

i tried the multiple counter plan in IDES server.

First i have created the Cycle sets in IP11Z in KMS

Then in IK01 i have create the Measuring point.

Then IK 11 i have create the measuring document.

Then i used the ip42 create maintenance plan

while saving it givivng messageNo counter assigned for performance-de

maintenance cyclespls advice what steps i need to follow for multiple counters

rgds

sp

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

After creating the cycle counter ,kindly use the same while creating multiple counter plan using IP43.if you have created the measuring point with the same characterisitic has specified in the cycle set ,system will automatically copied ,but if you have created no of measuring point then you system will prompt you with a dialog box where you can select from the last

kindly check whether the reference object you have used is same for plan and measuring point

regards

thyagarajan

Former Member
0 Kudos

Hi Experts,

I have checked that the charecteristic is same. But still it giving same error

pls help

rgds

sp

Former Member
0 Kudos

hi

In IK01 have you ticked on Measuring Point Is a Counter

Regards

Sujit Gujar