Multiple counter plan

Hi Experts,

i tried the multiple counter plan in IDES server.

First i have created the Cycle sets in IP11Z in KMS

Then in IK01 i have create the Measuring point.

Then IK 11 i have create the measuring document.

Then i used the ip42 create maintenance plan

while saving it givivng messageNo counter assigned for performance-de

maintenance cyclespls advice what steps i need to follow for multiple counters





In IK01 have you ticked on Measuring Point Is a Counter


Sujit Gujar