Confirmations in scheduling agreement

vijay_singh21
Contributor
0 Kudos

Dear All,

In a PO, I can 'manually' enter confirmations using confirmation control key AB.Is it not possible to do so in scheduling agreements?

Regards,

Vijay

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

In ME31L screen enter the details.

Then select the line item click on the item details in the tool bar.

There u will find the confirmations.

Check it out.

Regards,

Raman

vijay_singh21
Contributor
0 Kudos

I have already put a confimation control key in this field.Now I want to manually put confirmation control 'AB' by selecting the line, go to Item>Confirmations. Here I cannot edit and add my confirmation manually. Where can I put it?

former_member182609
Active Contributor
0 Kudos

sorry we can add ME38

Edited by: Sridhar Jayavarapu on Apr 6, 2009 1:37 PM

Former Member
0 Kudos

Hi,

Yes. Select the line item in ME31L and click additional data ( lens) and go to otger data here you acn find Confirmation control field and enter and save.

Regards

Ram

vijay_singh21
Contributor
0 Kudos

Any other ideas?

Former Member
0 Kudos

Hi,

It is possible to enter confirmations in ME31L while creating SA, after that it is not possible to change in ME32L.

Regards

Ram

Former Member
0 Kudos

Hi

It is possible to do the confirmations for Schedulling Agreement.

SPRO > MM > Sche.Agreement > Screen Layout >: Active the Confirmation Control

Maintain the Confirmation control key at item Level of the Sch. agreement

Maintain the delivery schedule

Check the process

regards

Prasanna

vijay_singh21
Contributor
0 Kudos

I do not think so. It is only after you have created a scheduling agreement that the vendor can send an acknowledgement. So, it should be possible for maintaining acknowledgements by ME32L.

Former Member
0 Kudos

Hi

It is possible to maintain the Confirmation control at ME31L. i have tested the same.

Kindly test the case and confirm

regards

Prasanna

vijay_singh21
Contributor
0 Kudos

Hi,

The confirmation control key is already maintained. The delivery schedule is also maintained, but the system does not allow me to enter order acknowledgement(AB) now.

Former Member
0 Kudos

Hi

It is allow me to do the acknowledgment at ME32L after the outputed,

Kindly check the Layout setting at SPRO

Regards

Prasanna

vijay_singh21
Contributor
0 Kudos

Prasanna,

Still no luck!!

The steps I am trying to do:

1. Create Scheduling Agreement(with a confirmation control key-consists of order acknowledgement and inbound delivery)

2. Maintain Delivery schedule

3. Maintain confirmation AB(This is whre I am stuck).

I hope I am not missing anything.

Regards,

VJ

vijay_singh21
Contributor
0 Kudos

Prasanna,

Got the solution. I have to maintain confirmations in ME38 and not in ME32L. Thanks for your effort.

Regards,

VJ

Former Member
0 Kudos

Hi,

Yes. Select the line item in ME31L and click additional data ( lens) and go to otger data here you acn find Confirmation control field and enter and save.

Regards

Ram