MRP for Project

Former Member
0 Kudos

Hi

Could you please tell me how to configure MRP for Project

and T.Code run MRP for Project and check requirement before&after run MRP

Check Project Stock ?

Thank and Best Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

you have to maintain the MRP VIews in the Material Master

MRP Type PD

requirement : "1" - Individual.

MD51 is for project MRP run

MBBS is the Project stock checking.

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Cao,

Regarding MRP for projects,all setting are standard from PS point of view.

Material has to maintained either 01-Indivial or 02 -collective Requirement.

You can maintain MRP type PD or reorder point for the material.

On the basis of material type whether the material is meant for internal production or for external procurement while running MRP at plant level or project system will create PR or planned order.

Muzamil

Former Member
0 Kudos

Are you sure that you can use reorder point planning for project stock? I don't believe that is the case.

Former Member
0 Kudos

Hi cao,

Pls check this settings also...

checking group

checking rule

scope of check

checking control

For network types

Regards,

S.Suresh.

former_member203108
Active Contributor
0 Kudos

In addition to that, u have to tick valuated or non-valuated project stock in project profile

Former Member
0 Kudos

Hi

Could you tell me what difference between valuated and non-valuated project stock.