Hi
Could you please tell me how to configure MRP for Project
and T.Code run MRP for Project and check requirement before&after run MRP
Check Project Stock ?
Thank and Best Regards,
hi
you have to maintain the MRP VIews in the Material Master
MRP Type PD
requirement : "1" - Individual.
MD51 is for project MRP run
MBBS is the Project stock checking.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Cao,
Regarding MRP for projects,all setting are standard from PS point of view.
Material has to maintained either 01-Indivial or 02 -collective Requirement.
You can maintain MRP type PD or reorder point for the material.
On the basis of material type whether the material is meant for internal production or for external procurement while running MRP at plant level or project system will create PR or planned order.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi cao,
Pls check this settings also...
checking group
checking rule
scope of check
checking control
For network types
Regards,
S.Suresh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In addition to that, u have to tick valuated or non-valuated project stock in project profile
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.