Will Anybody be able to help me with the following issue.

We have implemented Both Projects and Production modules.

NOw when I want to analyse the PLAN/ACTual COST/REVENUE Report -

S_ALR_87013531

The PRoduction Orders Planned Cost Is simply displayed in the

hierarchy under the respective WBS ,But What I require is that this

production Order Plan Cost should also affect the Total Plan Value Of

the WBS,In other words I need it to total UP.

If YOu Can Help.Thanks for The Same

Mercy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

Standard functionality of PS module doesnt considers Production order planned cost for Project cost plan as Production order is assigned order for the WBS.

u can add this planned cost thru CJ40 to the WBS.

Rgds

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Mercy,

Two settings required

1) OPSV as another user has already pointed out and here you could mention the order category (10 for production order, 20 for network) and the order type (production order type or network order type) and you could turn the "addit" indicator "ON"

2) Run the transaction CJEN for reconstructing the Project info Database.

You must be able to see the additive values on the WBS element level

Thanks,

Nithin

Former Member
0 Kudos

Hi All,

I had created a new Project with a new Production Order,and then run CJEN

But It some how doesnt seem to be working

I am not Quite sure y

Thnx for ur replies

Former Member
0 Kudos

Hi Mercy,

Goto T.Code OPSV. Against the Order category "10" (Production order), tick the indicator "Additional". This will add the order costs to the resp WBS.

bye

Pratap

Former Member
0 Kudos

Hi Pratap,

Thanks for the reply

But can i specify it for a particular network type

if so should it have the 'Assign Funds Indicator ' ticked and also should the

network have the planning control indicator ticked.

Thnx

Former Member
0 Kudos

Hi Mercy,

You cannot specify it for a particular network type. Keep the assigned funds indicator ticked.

What do you mean by the Planning control indicator?

bye

Pratap

Former Member
0 Kudos

Pratap,

Ive tried this,

Any other settings to be made

Thnx

Former Member
0 Kudos

Is it working or not? It has to work. I dont think there are any settings for this.

Pratap

former_member203108
Active Contributor
0 Kudos

If u tick the planning control indicator, it will not raise the assigned value.

Former Member
0 Kudos

Pratap,

it is not summing up the values still

Former Member
0 Kudos

Mercy, you try this by creating a new project and production order. Because such config may not be dynamically applilcable. Run a new cycle and let me know.

bye

Pratap

Former Member
0 Kudos

Hi Pratap,

Ive entered a new order it still doesnt seem to be working

anything from the Production Module

thnx

Former Member
0 Kudos

Just another doubt I basically want the Production Order Cost to Increase the

Project Planned Cost.

Thnx

Former Member
0 Kudos

Sorry for repeating my previous point. Did you create a new project also?

I want to know one more thing. In the plan/actual report, I think you are able to see the Production order under the WBS element, right? Does this planned cost include all the Prod costs, raw material costs and overheads?

Pratap

Former Member
0 Kudos

Hi ,

U can refer PLM 230 - Accounting In this text book the chapter for planned cost for the project clearly states that system doesnt considers Production order planned cost as project plan cost.