Planned cost in order

Former Member
0 Kudos

HI

I am not able to get the planned cost on order. After assigning component to the order, it should show me the planned cost as per the material price. I have done config. related to value categories. Where is the other integration point.

It seems plant specific as for the same material component with diff. plant i am able to see the cost.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

check whether you have assigned the costing variant to the order in the IMG for plan and actual case

regards

thyagarajan

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

For this go to SPRO, Functions & settings for Order Types -


Costing Data for Maintenance & Service Orders -


Assign Costing Parameters & Result Analysis Keys - Execute -


Goto details--


maintain control key PM01 for both the fields.

Sure ur problem will be solved

Regards,

krishna

Former Member
0 Kudos

For this the T.code is OIOF. Maintian Control key PM01 in both the fields.