on 04-04-2009 8:18 AM
hi
i created a project with wbs elements and internal activities now the planned cost is also been calculated on correctly say for example i have a structure of two levels and say the total cost of 2nd level wbs element will show in the 1st level wbs element say the total is 50000. but when i created a sales document value of say 60000 and after assigning the sales document with the 1st level wbs element the total cost is showing 10000-
and when ever i generate bill against the sales order the actual cost in the project planning board is showing the billed amount. and also when i generated revenue against the bill the actual revenue is also not showing.
am new to ps so can any one help me on this
what is going on
regards
subhro
ya answeres
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In the sales order check the document flow and ensure the accounting document has been created.
If the a/c doc has not created , then the actual cost will nt be shown.
That means ur document may b incomplete.
ashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
for revenue based costing,whenever the sales create the billing against the customer,the cost will be booked against the profitability segment with reference to sales order.
Make the account assignmnet in sales order aginst the WBS,so that when the billing created it will booked to WBS.Orelse you can book directly in salea order & later you can transfer to WBS by Result analysis key & transfer to project,latter you book to profitability segment.
Regards,
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.