Dear Gurus,

I have checked a few reports in like CNS41, CN52N, S_ALR_87013543 (act/plan/var cost element wise)

but nowhere I could find the planned v/s actual costs of material components planned in the Project.

Can some one help me with some report, where I can get desired data.

Regards,

VDS

Accepted Solutions (1)

Accepted Solutions (1)

stheurkar
Active Contributor
0 Kudos

Dear Rupesh,

I don't think so there will be any std.report in PS module to show plan vs actual cost of material component.

For looking plan vs actual cost in PS having many std reports but they don't show for material component.

I think for this you need to develop a Z report which will show Plan vs Actual cost of material component.

In CN52N report (Component overview report) you can add two fields one is for plan cost & other for actual cost.This can be one of possibilty you can try.Otherwise develop a new Z report for the same.

For this you need to take yr abaper's help.

Regard's

Sandeep

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Rupesh,

You can get from Hierarchal reports planned.actual/commitment report.

S_ALR_87013533

Muzamil

Former Member
0 Kudos

Hi,

The Planned /Actual cost will always displayed with respect to costelemnet only,not on the material or service you have consumed.

In KOB1 you can see only actual consumption for material wise.

The stock received & kept in storage you can find in MBBS.

If the requirement is like that then you have to develop ZDevelopment for reports.

Regards,