Scheduling transports into prod

0 Kudos

Hello,

We are running Solution Manager 7.0 SP15 and we have a requirement to import normal corrections into the production systems on Sunday morning at 4:30.

I for one do not want to wake up every Sunday to change the maintenance cycle of each system to "go-live" and then back to "development with release" in order to allow the transports to production.

There must be a way to automate/schedule this process.

Management wants to use only normal corrections for the Sunday transports.

Thank you!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Why would you want to change your Maintenance Cycle back to in development with release?

Once you finish your maintenance cycle every week you should create a new one

In order to move the transports into Q or P automatically you can either schedule a job for the report /TMWFLOW/SCMA_BTCH_SYNC_UC which runs every 10mins and thus imports all transport for a specific Project for a particular System and Client.

Another possibility is to schedule the automatic mass import of all transport in the Q/P-import queue, via STMS. This will schedule the Report TMS_BCI_START_SERVICE (jobname TMS_0000000001TMS_TP_IMPORT)

Nesimi