Hi Guru's,

Thanks for ur support.

As per the client requirement i need to have all days working calendar.They want that system should not restrict them if the day is non-working as the calendar used.

Is there any adverse effect of having all days working calendar for project.?

Regards,

Kamal Rana

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

The Factory Calender can be defined as per the requiremnet of the client.Define the factory calender in SCAL & assign all working day without any holiday.

Then assign this calender in the Project profile in planning board tab in default values.

So whenever you schedule the activities of Project then the system will consider all working day & schedule the job.

Regards,

Raj

Former Member
0 Kudos

Thanks for your support.

Answers (1)

Answers (1)

Former Member
0 Kudos

You can define your own calendras working and holiday in txn SCAL. Assign your Holiday calendar to Working calendar.In working Calendar you can define working days from Mon-Sun.

This will effcet mostly your schduling. So when the system schedules it will take into considerations all working days and calulate the duration of Activity.

Thanks

Sarang