Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Factory Calendar

Hi Guru's,

Thanks for ur support.

As per the client requirement i need to have all days working calendar.They want that system should not restrict them if the day is non-working as the calendar used.

Is there any adverse effect of having all days working calendar for project.?

Regards,

Kamal Rana

Former Member
Former Member replied

Hi,

The Factory Calender can be defined as per the requiremnet of the client.Define the factory calender in SCAL & assign all working day without any holiday.

Then assign this calender in the Project profile in planning board tab in default values.

So whenever you schedule the activities of Project then the system will consider all working day & schedule the job.

Regards,

Raj

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question