on 04-03-2009 1:37 PM
Dear Experts,
I am creating single cycle plant with performance based with couter reading.
1 I have crated a measuring point with counter in running hrs
2 Created a single cycle plan and given the couter no. there
3 Since i hv given 4000 hrs in plan, as soon as i update the document there should be a notification but it is not happening
Can any one clarify the issue
Thanks&Regards
N.Chandrasekhar
Hi
Check follwoing steps as per my knowledge may bay helpul to you...
:1.Create a char
2.Cterate Measuring point. in IK01 based on say eqipment.
Enter reference Object
Enter Cntr Overflow reading
Enter Annual Estimate.
3.go to IP41
4.Enter Short text And cysle per unit.
5.Enter Counter and reference euipment
6.Save & Syetem will prompt for start counter.
7.Go to IK11 ,create a mesuring document/Documents.
8.If Any defect is there then go to IW21 & crete Notification
Alternatly from IP21 also you can crete masuring docs.
Is it the same way you are executing single plan...
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can u plz elaborate your problem..
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear thyagarajan,
1 I hv created meas point with counter with specified equip
2 made document for that of 10 hrs
3 Created a single cycle plan giving reference same equip Cycly given 250 hrs, Entered the counter no there, call horizon 100, schedule 365 days.... while saving given no to save.....while scheduling IP10,
taken the counter ducument which i 1st saved 10 hrs... thn called 1st call and released and saved.
4. here with out entering that 250 hrs in ducument i am getting the notification............?
5. I have to get the notification after entering 250 only..
Why is happening like that
Hope you have under the issue
Regards
N.Chandraasekhar
hi
while executing IP10 you should not manually release the call ,after scheduling the plan just save it ,then as soon as you entering the measurement document and once it has reached 250 ,then while scheduling the plan in IP10 once again system will generate the call object
regards
thyagarajan