hi Gurus

Just wanted a confirmation

Commitments are created when a purchase requisition is created.

Is it possible to prevent commitments from being created when a purchase requisition is created.

thanks

Amit

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You will have to apply SAP Note:1307755 :Deactivating update of purchase requisition commitment.

Regards,

Amit

Former Member
0 Kudos

Hi Amit

Excellent note and looks very recent too, have you applied this one

Amit

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear,

The cost element you use as procurement and hit the PR,PO should not of cost element catageory 90(Stastistical).Use normal not the 90 then it will not deduct from budget and hit any commitment report .

This may solve ur requirement.

Sukhveeer.

Former Member
0 Kudos

hi

if the secondary cost element is not created then you will not able to see this commitments in reports.

Former Member
0 Kudos

As a standard SAP Practice , whenever Purchase requisition is created it consumes budget allocated to the project.

So logically it creates Commitment against project and budget.

Hence not possible.