I have to extend 150 cost centers validity period at a time.

Please provide solution for this.

Thanks and regards.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Frank,

Thank you for using the SAP SDN Forums,

In relation to your query please refer to the information contained in Note: 37093 for details on extending the validity period of a Cost Center

I hope this helps,

Kind Regards,

Brendan

iklovski
Active Contributor
0 Kudos

Hi,

You extend validity period by 'creating' the cost centre in the extended validity period (KS01). If you want to do it many cost centres, use LSMW tool. Simply record KS01 transaction or use standard programs/BAPI for cost centre creation.