FOLLOW ON DOCUMENT NOT CREATED IN BACKEND

Former Member
0 Kudos

Hello SRM Gurus,

We have implemented the N-level Shopping cart approval BADI BBP_WFL_APPROV_BADI for 2-level Approval for SC.Now the WF is operating perfectly but now the prob is that the follow-on-document is not being created in the backend.

When we check in tcode BBP_PD,it shows status as "ITEM IN TRANSFER PROCESS".

Has anyone come across this problem?Please help.

Regards,

Disha.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Disha,

In BBP_PD at the bottom in the "Messages" area, are there any error messages displaying?

Regards,

Paula

Former Member
0 Kudos

Hi Paula,

There was some problem with the Background jobs in the system....all the jobs were getting cancelled..i created a new job for CLEAN_REQREQ_UP and stared it again...it worked the PR got created..but still the reason for this cancellation is not known,...any idea on this??

regards,

Disha.

Former Member
0 Kudos

Hi try manually running clean_reqreq_up