on 04-02-2009 6:32 AM
Hi
BOMs items are exploded inside the project structure. The requirement is to create a PR for project specific items from project itself. (and not from MRP). For this WBS element and network activity have to be released.
Can we generalize on what instances release of network activity will fail. Some of the reasons could be as follows:
1. Purchase group not maintained for the material in the material master
2. Purchase views not maintained for the material in the material master
3. Accounting and costing views not maintained for the material
Kindly give your thoughts for any other reasons in which the network release will fail.
Regards
Srikrishna
error in cost calculation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.