KE24

Former Member
0 Kudos

Hi Experts,

The KE24 actuals data is not matching with the actuals of the budget sheet. Actuallly both must be equal. Can any body inform me wht may me the reason.

Thanks in Advance

Raman T S

Accepted Solutions (1)

Accepted Solutions (1)

venkatesh_kulkarni1
Active Participant
0 Kudos

Hi,

actually

KE24 is actual cost line items at operating concern level.... and it is depend on accounting based or costing based.... for repective operating concer which one u activated.

just check/

for project related please go through CJi3 actual cost line item and check..

venkatesh

Answers (1)

Answers (1)

Former Member
0 Kudos

Thanks Venkatesh for ur replay. i want to know abt the KKA2 T-code in which the actuals is not matching with the budget sheet. What may be the issue?

Thanks in advance