/SAPAPO/CIF310 - Plaaned Independent Reqs are Not processed

Former Member
0 Kudos

Hi

Planned Independent requirements are not CIFed from R3 into APO. it throwing as error when checked in /sapapo/ccr

R/3 order does not exist in SAP APO for product PRODUCT, location 1000

/SAPAPO/CIF310

please let me know, any clues to resolve this issue.

Thanks

JK

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

SMQ2 and SMQ1 are executed on Both R3 and APO and cleaned the Queues on both R3 and APO sides.

no success.

JK

Former Member
0 Kudos

After executing the delta report, please check the SMQ2 of APO. you should see the blocked queues. Please look for application log using /SAPAPO/C3 for detailed error message. My initial impression is that product does not exist at that location. If exists then check if it is assigned to active model.

Former Member
0 Kudos

Hello everybody.

After release Demand plan from APO to ERP I try transfer PIR to APO, but is generated error message "R/3 order does not exist in SAP APO for product XXXXX, location XXXX" in /sapapo/ccr.
If I create PIR manualy in MD61 in this case PIR is transfered to A

Former Member
0 Kudos

After 'Send to APO' is executed. still, Planned Independent Reqs are not processed.

JK

Former Member
0 Kudos

Hi Janikaram,

Please check, if there are any blocked queues exit. Then you have to process those Qs.

Thanks,

Satyajit

Edited by: Satyajit Patra on Apr 2, 2009 1:59 PM

Former Member
0 Kudos

I am not sure why this erro occure but you can push the PIR by doing a "Send to APO" for that order.