on 04-01-2009 11:04 AM
Hello experts,
I have a requirment of uploading the budgets for WBS elements in the system. Also need to handle adding the investment program for the WBS elements. If there any standard BAPI using which we can achieve this. I am trying to use the BAPI BAPI_PROJECT_MAINTAIN for updating the amounts and somehow I couldn't update the WBS.
I am thinking of using the recording and session method to achieve this. Before I make my decision, I would like to take some experts advice from u.
Thanks in advance.
Ganesh Khumse
Hi,
Try with the below BAPI
BAPI_BUS2054_CHANGE_MULTI
Regards
Bala Krishna