Network costing stored in CO version 1 or 2

Former Member
0 Kudos

Hi All,

Can we use the CO version 1 or 2 for network cost planning otherthan 0 and how?

I want to store the network cost planning in CO Version 1 or 2 and not in version 0.

Regards

Muzmail

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

closed

Former Member
0 Kudos

Hi,

The cost that comes from Work center / Activity Type can be stored at version 1 or 2. The required setting can be done at Costing Variant (OPL1).

Regards,

Amit

Edited by: Amit More on Apr 1, 2009 4:04 PM

Former Member
0 Kudos

Hi Amit.Amerash,

Actually the problem with my client is that they are planning materials/services to the project from time to time.There is no single time material planning so it will create problem while running RA because system will post wrong COS to the project.

So i was thinking that if possible to store network costing in version 1 and i can do manual cost planning in 0 for system to post exact COS .otherwise i have to tick off the addititive indicator for order cat 20 in OPSV.

I want to see both network cost planning and manual cost planning in the system.

Regards

Muzamil

Makal
Active Contributor
0 Kudos

Don't do both Manual & n/w costing.

Chose either n/w costing or manual costing.

Otherwise when u do Budgeting, it'll be problem.

Makal
Active Contributor
0 Kudos

For network costing, you cann't have CO version 0/1/2.

For n/w costing, it's always 0.

All costs for Networks are sent to Plan Version 0.