Hi!, we need to simulate a scheduling depending on dates introduced by user.
Does anybody know if its possible to schedule entire project via function or similar ECC 6.0?. CJ29 seems to be difficult becase log of changes are shown in ALV...
Thanks for your help!!!!!
Hello!,
Bapi_project_maintain has schedule method?.
Also if bapi_network_maintain could schedule all may networks. How could I ascend new dates to wbs elements and project?. Also, Could I access to scheduling result?.
My issue is tahe we need to do a kind of scheduling simulation. User could change a activity date (via constraint) and we have to schedule project taking into account this new date. If the result is not good for user, we have to delete the constraint and keep the project as it was before the process.
So, we need to schedule the project via bapi_network_maintain only if the bapi returns the scheduling results...
Any idea????
Thanks in advance for your help!!!!.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Have you considered using project simulations?
You can transfer your project to a simulation version. You can "play" with that project simulation scheduling it as you wish. If you like the result obtained, you can transfer the result back to your opertative project.
Search in the online help for further info on simulation versions.
hope this helps
Rgds
Martina
BAPI_NETWORK_MAINTAIN wil help u with scheduling.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.