Error or warning message when closing WBS element

Former Member
0 Kudos

Hello Friends,

Is it possible to issue any error or warning message while closing the account assigned WBS after balancing cost to zero on WBS by settlement and (commitment zero) fully completion of GR, but IR has not yet done that means PO is still open.

Thanks for the help.

Kris

Accepted Solutions (0)

Answers (2)

Answers (2)

virendra_pal
Active Contributor
0 Kudos

you should not use messages on closure for this

run ME5J report

or run a line item report on the GR/IR account

This should be checxked from logistics side not from WBS or projects

Former Member
0 Kudos

hi

check is there any user exit available and activate it

Former Member
0 Kudos

Hello AP, Thanks for reply.

I checked up but there is no user exit. Is there any solution for this?