WBS Costing Report

Former Member
0 Kudos

Hi Gurus,

We have a requirement of developing WBS costing Report( detailed and summary) in 3.1i version.The specifications considered are as per below.

Actual cost details been captured from relevent POs and Project related Orders aganist WBS, However, for planned cost details, we are finding some discrepancies aganst std, SAP report.

Could you please clarify the following?

How to capture planned cost aganist WBS( ex: POs etc..), what are all the areas need to be covered?

Has anybody developed Z report or the above? if so, please provide the specs/functionality

We had refered relevent SAP std reports ( CJ7M, CJI4) for getting required inputs, but no luck!

Thanks in advance,

Kiran

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI,

Inorder to get all the actual costs on activity which is actually on WBS. You can do an enhancement. This enhancement should find the all POs against PR which belongs to an activity and will repost the costs that is being posted on WBS on GR to the concerned activity.

Regards,

Anjali

Answers (2)

Answers (2)

Former Member
0 Kudos

hi

refer table cosp & coss

pass the object number of wbs and select the value type = 1 and get the plan values.

ashis

Former Member
0 Kudos

hi

the Structure RPSCO contains all the data of costs