on 03-30-2009 12:55 PM
Hi,
I am having a tough time handling this requirement. Pls help.
I have a scenario, where i want system to propose a new finish date on every schedule update on the basis of current actual data.
For example,
An activity has a duration of 10 days and work of 100 m3. start date: 1st Apr & finish date is 10th Apr.
And activity is linearly distributed.On 5th Apr, if confirmation is 40 m3 of work completion instead of a planned completion of 50 m3,
then on re-scheduling, system should propose a new finish date for the activity. ie. for remaining 60 m3,
it shud automatically add another 8 days (60/8 = 8 approx.because the current rate of work is 40hrs/5 days= 8 hrs per day) to the current actual finsih date ( 5th Apr) and hence on next schedule update, the current finish date shud be 5 + 8=13th April instead of 10th april.
Regards,
hi
check the scheduling type you used.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.