on 03-30-2009 4:14 AM
Hi Gurus,
I had installed SAP Solution Manager 4.0(32bit) on HP DL360 32bit (RAM:2GB, HD:150GB).
OS: Windows2003 SR2
DB: Oracle 10G.
I logged on 'SAP Management Console' and found the status of 'Process list' of 'SLM 0' as ABAP was yellow.
(Thd status of 'Process list' of 'SLM1' as Java was green.)
The status of process 'disp+work.EXE' is always:
'Running but dialog Queue standstill, J2EE status info unavailable.'
OR
'Running,Message Server connectionok,Dialog Queue time: 0.00sec, J2EE status info unavailable.'
I tryed to restart OS and 'SLM 0' as ABAP many times.
But the status of process 'disp+work.EXE' is always 'Stopped' at the end.
How should I do?
Thanks!
Jason
Hi
As samrat said its the problem with listner service
start>Run>services.msc check for listener service is started
also check this link for more information
http://download-east.oracle.com/docs/cd/B10501_01/network.920/a96580/listener.htm
Regards
Uday
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I wanna post the whole content of log file 'dev_disp' here. But it's a pity the number of characters of 'dev_disp' beyond the limit of the forum. How can I post here? I don't know.
Edited by: jason xu on Mar 30, 2009 5:25 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.