Hi

I would be performing Demand Planning on a weekly bucket. Week starts from Saturday and Ends on Friday. The Planning will be performed for the six future month.

Can anyone suggest, how it can be done and If Fiscal Year Variant has to be used, then what will be the definition of the variant.

The financial year is from 1st jan to 31st Dec

Looking forward to a solution.

Regards,

Anoop

Edited by: Anoop Sahu on Mar 29, 2009 5:14 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can define a fiscal year variant with 52 weeks and specify the last day as a friday in every period...

To carry out planning for 6 future months only..you may define a Time bucket profile for 6 months and use this in the dataview definition.Use the above fiscal year variant in this Time bucket profile