on 03-27-2009 11:07 AM
I have done time recording through CAT2 , transfered to project through CATA/CAT5 after approval of time recording. Still cost is not updated in the report what may be the reason?????
In which separate reports I can see the approval of time recording and correct transfer to project.
-
if u r booking time with respect to activity type,
then chk the cost rate maintained in KP26 for that activity type in that specific period.
ashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Goto CN48N and verify if a confirmation has been posted for these hours against the project's network activity. If it has been, and the cost has not been updated on the project (looking at CJI3 or such report), then goto txn COFC and see if there is an error for reprocessing cost update item for the network. If you look at the messages in this transaction, it should give you an idea as to why cost has not been updated.
If the confirmation itself has not been posted in CN48N, then goto CN30 to see if there are any errors that need to be corrected and the confirmation reprocessed.