Cost booking in CATS

Former Member
0 Kudos

I have done time recording through CAT2 , transfered to project through CATA/CAT5 after approval of time recording. Still cost is not updated in the report what may be the reason?????

In which separate reports I can see the approval of time recording and correct transfer to project.

-


Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

if u r booking time with respect to activity type,

then chk the cost rate maintained in KP26 for that activity type in that specific period.

ashis

Former Member
0 Kudos

Rate has been maintained for the activity against desired period.

Former Member
0 Kudos

chk d cost center for that employee.....is it same as activity type cost center.

ashis

Former Member
0 Kudos

Thank you. Cost center for the activity type and employee is same.

Former Member
0 Kudos

Goto CN48N and verify if a confirmation has been posted for these hours against the project's network activity. If it has been, and the cost has not been updated on the project (looking at CJI3 or such report), then goto txn COFC and see if there is an error for reprocessing cost update item for the network. If you look at the messages in this transaction, it should give you an idea as to why cost has not been updated.

If the confirmation itself has not been posted in CN48N, then goto CN30 to see if there are any errors that need to be corrected and the confirmation reprocessed.