How to show "Degree of processing" on Network Activity as a Date bar

Former Member
0 Kudos

Hi,

when confirming Network Internal Activities with a "Degree of processing" in percent, is it possible to show a corresponding Date bar in the Actual Dates at the Project Planning board ?

Or any other way to show the "Degree of processing" in percent as a Date bar.

Thanks for the advice

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

that was not what I have meant.

I´m looking for the "Degree of processing" not the actual "start-end" Date bar.

Former Member
0 Kudos

Hi,

I am not sure about this.

You can have a look at CNE5 report for Project Progress.

Regards,

Amit

Former Member
0 Kudos

Hi,

Yes, you can show actual date bar in PPB.

In PPB Goto> Settings>Planning Board Assistant>Date Display on Activity Tab>Select set of dates as Actual.

Regards,

Amit