Dear All,
I have 2 project profiles, customer and R & D.
For customer project profile, i can set 3 operating indicators - Planning, Billing, A/c assingment.
For R & D project, i have only billing and a/c assignment operating indicators.
How can i add planning element for R & D project profile - to the WBS element?
Please help me.
Regards,
Pritam
Hi,
Goto OPUK>Click on influencing> Select Project Profile--->Put Planning Element as Input Field.
Regards,