Hi PS gurus
Just wanted to know if i could search for Project definition/WBS having a particular System status using the project information system.
I think is possible using the Selection (Status profile) but i was wondering if it is also possible using the Status Combination code.There are 14 standard Status combination codes already defined by SAP in the system. I was just wondering if i could start my search by using one of these codes in the dynamic selection.
I did try using that but the search wasnt successful. just wanted help so that to understand if i am doing something wrong in the Status Combination code process
Amit
Hi Cristina,
After having investigated this in detail, I have found that we can select the objects to be viewed in cns41 report by selecting dynamic selections and navigating to status combination code (Under Master data WBS element). The system shall only find project elements with specific status combinations and stores this information in the PRPS_STATUS (Technical field). The project elements with the specific status combination get immediately displayed by selecting dynamic selections.
Check whether an enhancement can be developed within cns41 to add this PRPS_STATUS(Combo Code) as an extra field while viewing the structure overview report.
Regards
Varun Rudrabhatla
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Cristina,
The field is used to make the filter based on status faster. Generally the filter based on status will be quite slow as the data is fetched from the JEST table which will be quite big. This enhancements adds a field called status combination code in basic tables like PROJ,PRPS ,AUFK,AFVC. This means that this field can be used in dynamic selection in the reports.
However once activated we should define status combinations that are meaningful for our dynamic searches. Lets say we define a new status combination 0014 -- REL and BUDG.. As soon any object like, lets say WBS, have these statuses of REL and BUDG the value 0014 will be set in the field status combination code in table PRPS. So while using dynamic selection you can filter WBS elements with status combination code 0014 and you will get only objects that have status REL and BUDG active.
Regards,
Jindow Joseph.
Hello Joseph
The problem is that the functionality is already working, I just have the values in PROJ, PRPS and other tables. But when I try to use the report with dinamic seach by (Combo code) I can't find it.
So, my doubt is if I need to add this field by enhancement and which enhancement should I use.
Regards
Cristina Romanato
Hi,
Have a look on this document, might be helpful.
Add new field on dynamic selection screen of any report
thanks & reg,
Sam
Hi Critina,
As the functionality is active, it should be already available in the dynamic selection. No additional steps are required.
Check whether the database is rightly activated. In SE11 open the table PROJ , goto menu option Utilities--> Database object--> Database utility. Then click on the button activate and adjust database. Repeat the process for other tables.
Hi Amit, I think what you are asking is how do you use this field? After you turn on EhP 3, you will see that PRPS and PROJ now have a new field added to them (PRPS_STATUS). I don't think you explicitly populate it in Cj20N instead it is automatically populated based on the configured status combos. Then when you run a structure report like CN43N goto Dynamic Selections (SHift+F4) and you will see under folder "master data WBS" the field 'Status Combo Code" as a field you can use for selections to speed up the reports instead of the old status profiles.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Virendar
I know its part of the new Ehp 3 support pack, but i am not getting the desired results.
Any way i have another question.Have you got the Ehp3 implemented. We have got it implemented for our client.there is a feature in the EHp3 where when u save the project through the project builder, it doesnt throw u out of the transaction. but even though Ehp3 is implemented i cannot see this function working have u got any clue how des this new feature get activated
the "combination codes" that you refer are nothing but preconfigured status profiles to give you an idea
the selection profile is to be netered in the status selection field on the report and not on dynamic selection
you should be able to select projects (definition or WBS or networks etc) based on these profiles, but depending on your reuqirement you may to configure them
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.