NO fixing SNP Orders

Former Member
0 Kudos

HI SNP Gurus!!

I would like not ot getting SNP fixed orders after heuristic execution, I mean, I need unfixed orders?

Does anybody know how can I do that?

Thanks in advance to everyone

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

Set SNP procuduction Horizon within this horizon SNP Heuristics plan Unfixed orders after that it will plan fixed order.

Mj

Former Member
0 Kudos

If you are on 5.1, use the product master setting on the SNP1 tab. If you are less, then write a FM that calls the order OM/DM routines and change the value in LC (remember to create a SIM)