I am looking for a report which will help me to report on combination of all of the above. In PS I dont see any report which will allow me to track back to my Asset class on AUC or AUC or even the fixed Asset.
I see the reports in Asset in which I can pull WBS from dynamic selection, but this will work for Direct Asset Acquisition and not on AUC process. I want to track back mmy WBS from FXA/AUC and Asset class, such that I should be able to report on Asset class.
What will be the best option? Can I define Proj types as per Asset classes n then use for reporting or go for User defined fields and then report on them.
Awating replies.
Thanks
Sarang
You may also check following reports for their possible use:
S_ALR_87011946 - List of Origins by Cost Elements
S_ALR_87012930 - List of Origins of Asset Charges
with regards,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
in CJI3 or CJ70 you can get the values posted to WBS elements.
in AW01N by selecting the AUC asset you can get the values posted to it.
S_ALR_87011964 - ... by Asset Class
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.