I am looking for a report which will help me to report on combination of all of the above. In PS I dont see any report which will allow me to track back to my Asset class on AUC or AUC or even the fixed Asset.

I see the reports in Asset in which I can pull WBS from dynamic selection, but this will work for Direct Asset Acquisition and not on AUC process. I want to track back mmy WBS from FXA/AUC and Asset class, such that I should be able to report on Asset class.

What will be the best option? Can I define Proj types as per Asset classes n then use for reporting or go for User defined fields and then report on them.

Awating replies.

Thanks

Sarang

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You may also check following reports for their possible use:

S_ALR_87011946 - List of Origins by Cost Elements

S_ALR_87012930 - List of Origins of Asset Charges

with regards,

Ravi

Former Member
0 Kudos

Thanks Ravi and AP.

S_ALR_87012930 - List of Origins of Asset Charges is close to what I am looking for.

AP - CJI3/CJID/CJ70 only shows value when AUC exsists (partial/period settlement is done to AUC) , however when Asset is completed these reports doesnt show anything.

Thanks

Sarang

virendra_pal
Active Contributor
0 Kudos

go to SE38 and run these reports and check if they meet your requirements

RAHERK01 - these is what I had used

RAHERK02

Former Member
0 Kudos

Thanks.

Clsoing the loop.

Answers (2)

Answers (2)

Former Member
0 Kudos

closed

Former Member
0 Kudos

hi

in CJI3 or CJ70 you can get the values posted to WBS elements.

in AW01N by selecting the AUC asset you can get the values posted to it.

S_ALR_87011964 - ... by Asset Class