Hello SRM Gurus...

We are in Classic Scenario and SRM 5.0

MY Requirement is..

We have a user who creates a SC with attachment and w.r.t SC a PO is created in backend.

The attachment would flow to Backend PO as standard.

The PO is then sent to Vendor by Output E-Mail,

when the vendor receives the Mail,he dosent get the attachment.

We need to deleop/configure the system so that the attachement goes along with the PO.

Please suggest the possible ways we can achive this.any thing to be done on MM part?

Thanks

Sanjeev

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Sanjeeva,

Please refer the below link.

You need to configure the DMS (Document Management system) in order to avail this functionality.

http://help.sap.com/saphelp_srm50/helpdata/en/49/b32640632cea01e10000000a155106/content.htm

http://help.sap.com/saphelp_srm30/helpdata/en/ea/59bc392ceddf3ce10000000a114084/content.htm

Best Regards,