on 03-25-2009 11:53 AM
Hi
I am a PM Consultant, i am about to learn PS module. What are the requirements...
Is there any flow for PS module...
can any one guide me ?
- Pithan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Network process & activity to network are everything same as maintenance process only.
only difference is the WBS.That is upper hierarchy of PS.
Project- WBS- Network ( Maint order)--- Activity (like Operations in maintenance).
If you are familiar with the Capital investment order in PM.You can understand PS some what.
Regards,
Raj