Unable to release transport request for modified Planning book from Dev Sys

Former Member
0 Kudos

Hi All

can someone advice on this:

We have included a new key figure to our existing Planning book, which is already defined in Planning Area. This key figure is just getting shipping data for comparison and is not having any impact on macros also. We inserted key figure and set the attributes as output only and all looks good in Development system. But when we created transportation request and trying to release request it is giving error "Test Call of transport control program (tp) ended with return code 0208" Message no: TK094

can any one advice on this

KV

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

Please check with Basis team. I think this is not related to planning book that you are trying to export. A look in the message text gives the following:

Check the following points:

Feasibility of the transport control program tp

Parameter settings in the transport profile

Availability of the transport directory and the subdirectories (cofiles, data, log, sapnames, bin)

Write authorization for the subdirectories

Write authorization for the files of the subdirectories cofiles, data, log, sapnames

Release the request again when the error has been removed.

Hope this helps.

Warm regds,

Ashutosh

Former Member
0 Kudos

Hi All

Thanks for your inputs , This is a Basis issue , they resolved the issue and ow the transport request is released.

KV

Answers (1)

Answers (1)

aparna_ranganathan
Active Contributor
0 Kudos

Hi ,

To the best of my knowledge the procedure to transport the changes is as follows

1) Create a transport request for the key figure and release it

2) Go to /n/sapapo/msdp_admin and open your planning area and click on menu option goto and select transport connection - it will open up the manual transport connection link. Give your planning book and planning area names - generate the transport and then release it.

Since you have added a new key figure the planning area will be deinitialised - so you have to reintialise your planning area. But this will lead to the loss of live cache key figure values. So make sure you back up the live cache data *BEFORE RELEASING THE TRANSPORT* .

Thanks

Saradha