Dear Friends
I have created BOM, transferred BOM (CN33) to project activity.
I did run MRP (MD51). System has created reservation. Now how this reservation be converted in to planned order/ PR based on the available stock.
thanks
goto MD04..enter the corresponding Material no. and plant...the system will show u the reservation for the material.....under your project stock...u will see 'PurRqs' (if there is a PR) or 'PldOrd'(if there is planned order)....click the detail icon...in the pop window u will see 'to purchase order' or 'to prodn order'..click that it will take you to PO screen / Prodn order screen...this is wat i know..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What is the difference between MD51 & MD01? As for as I know, for projects we have to run MD51 for MRP. MD01 is again MRP Run T-code in MM.
Since I have have already run MD51, do I again run MD01?
In MD01 system asks for "Scope of planning", what exactly it is? & what are releavant IMG settings required for ir? What "MRP control parameters" should be used?
Thanks
Thanks a lot Ahmed.
1.In Project profile, I have already selected, "project stock"
2.Here I have missed to maintain ind/coll, in MRP4 screen.
3.During material assignment I was selecting "reservation for network".
Regarding point no.2:
Do I need to maintain ind/coll in MRP4 screen, for header item (in BOM) only or for all the material in a particular BOM?
Thanks
It will create Planned order for those material whose having reservartion after creating Bom Transfer..
U did Bom Transfer....so while bom transfer..system will create reservations for materials..
When u will do MD51 project MRP run..then the sytem will create planned order...that planned order u have to convert it into production order manually..after that release it ...do GR so that material will go in stock...further u can do GI for particular production order.
Hope u understand the process.
Regards,
ANSAR
Ansar Thanks for reply.
Let me put my question straight forward.
I have created BOM, attached header material to internal activity (system creates reservation the moment I attach material to activity). I did BOM transfer.
Then I did run MD51. System does not create planned order for the header material. But for other components, PR is getting generated.
The issue is only with header material, for which, MD51 is not generating planned order for header material.
I hope I have put my problem in right way.
Please help.