on 03-24-2009 9:17 AM
Dear Gurus,
My scenario is as follows -
I have created project structure,
1. PROJECT DEFINITION(1).
2. WBS ELEMENT
3. NETWORK
4. ACTIVITIES
In ourb= scenario there are no. of activity assign under a single network but my problem is that, when i released NETWORK all the activities under that network gets released.
Is there any control for activity release, so that we release activity according to our requirement.
THANKS.
Regards,
RAKESH
Hi
I n addition of above problem, i am fecing one problem i.e. once i release project all the WBSE, NETWORK and ACTIVITY get released. but i want to release each & every thing as per our requirement.
Please give me solution on this issue.
Thanks,
RAKESH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Release idependent activity which you required not network header.
Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.