Dynamic selection for work centre in CJI3 - Actual Costs/Revenues not work

Former Member
0 Kudos

Hello Experts,

Can anyone let me know what is goin wrong in my CJI3 report or am I missing any setting for dynamic selection???

I need to have CJI3 report with selection on workcentre level, but when I run the report I shows me the cost of all the Workcentre. I need to have cost of single workcentre.

Regards,

Tushar

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

in the CJI3 screen enter network number and not the project definition

set dy sels for net act master data for work centre

execute

you should be ok

unfortunately in CJI3 you do not get work centre as a field

you can double check results using CN47N