Cost element XXXXX For network activity "network" / "act" does not exist

Former Member
0 Kudos

Hi Experts,

I am getting an error when saving a project. We have defined a default cost element for external activities but, only in some tasks when saving the project we are getting the error

Cost element XXXXXXXX For network activity XXXXXXX / XXXX does not exist

The cost element is created, and assigned properly.

Any idea on what could be the problem?

Kind regards,

Neil

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

check if cost element has validity for the current year

Former Member
0 Kudos

Hi,

The cost element is created (in fact is one of the possible values in the matchcode). It is valid from a former date than the beginning of the task until 12.31.9999.

Any other idea?

Thanks!

Neil

virendra_pal
Active Contributor
0 Kudos

always write the message number

can you give me the message number please

Former Member
0 Kudos

Sure,

Its CK204.

Thanks!

Neil

Former Member
0 Kudos

hi

check this sap Note 1277967 - Error mesage CK204 when changing internal activity

virendra_pal
Active Contributor
0 Kudos

see how quickly once you give error message number the solution is there

apply note as suggested by AP

Former Member
0 Kudos

Thank you both.

I will inform you if the note application fixes it!

Former Member
0 Kudos

Hi,

It's solved!

Thanks for your help!!

Kind regards,

Neil

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

please check whether the cost element is created otherwise create the same in KA01.