on 03-23-2009 11:10 AM
Hi,
We all know that COSP and COSS tables show Cost totals for external and internal postings and you can refer to them through the object no. from table PRPS.
But what about if you save a snapshot-version where are this information for already done external and internal postings?
We are going to create a report which show this information and compare with the actual from project.
Please put some light to this issue,
until then best regards
Jose Marin
The information is in table RPSCO.