Is it possible to have the billing plan dates as per the schedule lines of the items using the billing plan configuration(either via either periodic billing plan or milestone billing)

for e.g. for a line item - qty 10(value 1000), delivery schedule is as follows

10-Mar-2009 - qty to be delivered is 6

02-Apr-2009 - qty to be delivered is 4

( dates and qty would be decided as per the customer needs. No periodic differences between dates).

My expected billing plan should be as follows

10-Mar-2009 - value to be billed is 600

02-Mar-2009- value to be billed is 400

if yes, please let me know.

Thanks in Advance for your answers.

Regards,

Madhuri

Accepted Solutions (1)

Accepted Solutions (1)

former_member217082
Active Contributor
0 Kudos

Hi Madhuri

For your requirement you have do go with the scheduling agreement and maintain periodic billing and as per the periodic billing and the delivery quantity dates the stock can be delivered and billing can also be done