hi friends,
i configured entire ebp and run the application in web.but i didnt get one thing .confirmation has done in srm.material document has created in the backend and updated in the status of shopping cart.my doubt is ,the confirmation activty can also be done is r/3. but how can we differentiate or come to know that which document can be created by which component(i mean r/3 or srm).
thx and best regards
Hi chakri,
Confirmations / Invoices can do either in SRM or in R/3.
If you set up customer distribution model in SRM, then only we can do the confirmation/invoice in SRM,
these confirmation will transfer to tht R/3 through IDOC.
Based on the confirmation created in SRM respective GR document created in R/3
Hope ur douts clarified..
Thanks