on 03-23-2009 6:19 AM
hai ,
i have worked in 001 client and configured self service procurement completely.and later i was doing plan driven procurement and maintained v_t160pr ,and v_t160 ex and run the report bbp_extrun_transfer in r/3.but the system had given a warning message as below
sap event management communication aborted,no AOTS defined.
*Eh creation not permitted:AOT evaluation skipped
*event message sending not permitted:event type evaluation skipped.
i thought that i have missed some configuration in r/3.am i correct?if it is, can anyone please give me the suggestions what are all the remaining things i have to configure in r/3.
thanks and best regards
chakri
Hi Chandra,
You must have executed BBP_EXTREQ_TRANSFER this program. check it up.
this table brings all information to EBP from EPRTRANS table. first check EPROFILE field was set in eBan table.
and also see in sourcing cockpit wheter your request ahve reached or not.
check points smq1,smq2 ,slg1
regards
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi chandra
please refer kathir's article.
regards
Muthu