on 03-21-2009 12:50 PM
Dear Experts,
Please help for following requiremnt as I am new to PS.
1) How PP is integrated with PS?
2) How to Plan for a FG Material for which components are defined under PS?
Following should be incorporated in Planning of FG.
a. Planning of FG Material requirement on monthly basis at Plant level.
b. Procurement planning of inputs (RM) at WBS under common project.
c. Issue of FG to various Projects on a WBS.
Regards,
Tanuj Parikh
process will be as follows
In PS raise a demand for a FG in the network
the FG is a BOM consisting of various materials required for production
then run MRP to generate planned order to produce FG and then create production order in PP
carry out PP order as usual and issue FG to inventory
then issue to network from inventory
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In PS raise a demand for a FG in the network - txn CJ20N to assign materila to network, material master relevant for MRP, all the necessary network and project profiles for project creation
the FG is a BOM consisting of various materials required for production - maintain BOM txn CS01
then run MRP to generate planned order to produce FG and then create production order in PP
carry out PP order as usual and issue FG to inventory - MRP txn MD51, config for planned order type, production order type and all relevant PP config for order execution
then issue to network from inventory - goods issue MIGO