on 03-21-2009 5:59 AM
Dear experts,
i want to control that new materials cannot be added to sales orders for which billing have been performed. Currently i can add the new materials in the sales order for which billing is completed , not only materilas i can change the header data also.
my requirement is sales order must be in grey mode as soon as billing is done.
regards
abhi
Dear Abinav
Create a sales cycle and delivery and pgi and billing
Then input the sales order no in VA02 (change mode) and try to add an extra material and try to open up the sales order
There will be a warning message from the system
Double click the warning message and see the message no
This is definately in V4 class
Go to OVAH change from warning to error that message no
Right now i dont have SAP access to tell you the exact message no
But this i have done and controlled thro OVAH changes sometime back with simple customization
Regards
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try with any of the following sale order user exits
- User exits in the program MV45AFZZ - USEREXIT_READ_DOCUMENT
- User-Exits in program MV45AFZB - USEREXIT_CHECK_VBAK
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.