STO changed manually in R/3 but not reflected in APO the changed STO

Former Member
0 Kudos

Hi,

I am facing an issue where APO ( CTM Plan) generated Inter plant Transfer req. (converted to STO in R/3) but user manually changed the date in STO but the changed date did'nt reflected in APO.

I ran Delta report(CCR) and found it stuck in the CCR report with error message 181 saying "Schedule line does not exit".

Please provide your views.

Thanks,

Dipankar

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Dipankar,

In addition to what Visu has suggested, please check CIF application log in APO when you are performing CCR. It can be seen in transaction /n/SAPAPO/C3. Here you will be able to find detail error description.

Best regards,

Vaibhav

Former Member
0 Kudos

Hi,

Is the STO in APO first place? Did it ever make it to APO? It can also be that there is some contradiction for the date set by the user in R/3 with the date that can be set in APO. Check if there is a transportation calendar in the transportation lane or shipping or receiving calendars for the plant or DC. If they have a calendar that only allows Tuesdays and if the user set it to Thursday, it can block it.

Also check the system logs CFG1 in R/3 for the time the STO was changed. That can give you a clue of what's happening.