I have a requirement for my client to configure settings for Sales order ATP for Make to Project

what is make to project mean? is that Make to order scenario? i am not very sure on this. I looked at some standard SAP material for Made to order - Project stock scenario.

is this the one i am searching for? pls guide me to have some better understanding on this.

Good rating points will be given for valuable inputs

Accepted Solutions (1)

Accepted Solutions (1)

sarthak_mohantysd
Active Contributor
0 Kudos

Hello,

I think it is related to Creation of project using the T-code "CJ20N" completely related to PS module.

Correct me if i am wrong on this.

Regards,

SARTHAK

Answers (2)

Answers (2)

Former Member
0 Kudos

Researched and found the settings that needed to be done

Former Member
0 Kudos

Anand,

There is an Availability Check Process which is to be configured under Project systems the path is as follows

1. IMG --> PS --> Resources --> Maintain Control parameters for the Availability Check

2. IMG --> PS --> Material --> Availability Check

3. IMG --> PS --> Material --> Control of sales order related production

Check the above mentioned path